Dubai’s water infrastructure is set for a major expansion after Dubai Electricity and Water Authority and Acwa signed agreements worth AED 1.76 billion, or about USD 478 million, for the second phase of the Hassyan seawater reverse osmosis desalination project. The deal covers both a Water Purchase Agreement and a Shareholder Agreement, advancing a project designed to strengthen the emirate’s long-term water security. Once the new phase is added to the existing development, Hassyan is expected to become the world’s largest seawater reverse osmosis desalination facility, with total production capacity reaching 240 million imperial gallons per day.
Second phase adds major capacity
The new phase will provide around 60 million imperial gallons per day, equivalent to approximately 272,000 cubic metres of desalinated water. It will operate under a 30-year Water Purchase Agreement, giving the project a long-term framework for production and supply.
The agreements were signed by Saeed Mohammed Al Tayer, Managing Director and CEO of DEWA, and Mohammad Abunayyan, Founder and Chairman of Acwa, in the presence of officials from both organisations.
Joint company to deliver project
A dedicated project company will oversee development, financing, construction and operation of the plant. DEWA will hold a 60% stake in the company, while Acwa will own the remaining 40%.
The second phase builds on Hassyan’s first phase, which has a planned capacity of 180 million imperial gallons per day and involves investment of AED 3.357 billion. That initial phase was developed as DEWA’s first project using the Independent Water Producer model.
Supporting Dubai’s water security
DEWA said the expansion reflects its focus on sustainable desalination, modern technologies and reliable infrastructure to meet Dubai’s rising demand for water. The authority also linked the project to broader national and local strategies, including the UAE Water Security Strategy 2036, the Dubai Clean Energy Strategy 2050 and the country’s net-zero ambitions.
Acwa said the partnership builds on more than a decade of cooperation in Dubai’s power and water sectors and will support efficient, large-scale infrastructure delivery.
Capacity target for 2029
When both Hassyan phases are complete, Dubai’s total desalinated water production capacity is expected to reach about 735 million imperial gallons per day by 2029, reinforcing the emirate’s resilience as its population and economy continue to grow.